Client: Buckingham Group Contracting Ltd
Value: £275k (L&P Only)
Date: Aug 2017
Duration: 16 Weeks

Project Goldfinger – Britvic Rugby Extension – Deep Drainage, Linear Drainage, Ducting & Kerbs
This project involved the extension to the Britvic facility in Rugby and our works included all drainage including deep drainage upto 5m deep, gullies, linear drainage, reinstatement of RC slabs where runs passed through existing live areas, new kerb lines including both standard HB kerbs and Trief kerbs, installation of large interceptor tank, concrete infill behind kerbs and multiple ducting runs and associated chambers.
Careful planning with our Client was required on a daily basis as there were many other contractors on the site and the interface between these was key to ensure the programme was maintained. Ensuring the correct resources and temporary works were in place ensured the success of this works package along with emergency plans which were in place should they have been required. Working around a live operational site, other contractors and existing services proved challenging but one our site team adapted superbly to to ensure the works progressed as required. This was an extremely busy and challenging site and a credit to our team to complete safely.


• Deep drainage both FW & SW
• MH construction
• HB Kerbs and Trief Kerbs
• Ducting and chambers
• Working around live services / operational facility
• Installation of large Puraceptor
• Temporary Works
• Reinstatement of areas to match existing
• RC slabs
• Testing of drainage
Other Projects

Our Clients






















Get in Touch
Talk to us today to see how we can help you with your project.